The machines a septic install needs, read from the system the design calls for: each job that design demands, the machine that does it, and the coverage every machine brings with it.

A hub-and-spoke diagram. At the center is the system the design calls for, because the system type sets the equipment list. The first spoke is the digging machine, an excavator or a backhoe, chosen by reach, access and soil. The second is grade control, a laser, builder’s level or transit, so the crew digs to elevation without over-digging. The third is low-ground-pressure gear, which keeps weight and smearing off the soil treatment area. The fourth is loaders, skid steers and trenchers, which move spoil, spread fill and backfill. The fifth is a planned lift to set the tank, with tag lines and no one under the load. The sixth is trench protection, shoring, sloping or a trench box where the depth calls for it. The last spoke is contractors equipment coverage, because each machine is both an asset you can lose and a source of claims. No figures are shown.

The equipment needed to install a septic system comes down to a handful of machines: an excavator or backhoe to dig, a laser or builder’s level to hold grade, loaders to move and backfill material, low-ground-pressure gear to protect the soil, a safe way to set the tank, and trench protection. The system type decides the rest.

Start with the system the design calls for

The system type sets the equipment list, so read the design before you line up machines. The EPA’s overview of septic system types describes a conventional system as one that “consists of a septic tank and a trench or bed” drainfield, and says design varies with soil, slope, lot size and local regulations.

Beyond the conventional layout, each design adds its own demands. The EPA names “increased ease of delivery and construction” as the main advantage of chamber systems. Drip distribution places laterals in the top layer of soil but needs a large dose tank. Mound systems pump effluent from a pump chamber to a sand mound built on site, and sand filters can be built above or below ground, often in a PVC-lined or concrete box. A mound or sand filter job means more imported material, more hauling and more time on a loader than a gravity trench job, and the pump chamber is one more buried, watertight tank to set.

The digging machine: excavator or backhoe

Every install needs one primary digging machine, and for most crews that is an excavator or a backhoe. Extension guidance shows how central the backhoe is. The University of Missouri’s homeowner guide to septic tank and absorption field systems describes a soil evaluation in which a backhoe digs one or more 4- to 6-foot deep pits, and its worked trench example assumes a backhoe with a 2-foot wide bucket.

The choice between the two usually turns on reach, site access, spoil handling and what your crew runs well. An excavator gives reach and swing for tank holes and tree removal; a backhoe travels between sites and handles lighter loading. Minnesota’s onsite program notes that an excavator may be the efficient tool for removing trees, with a warning to “be careful to limit compaction of the STA”, the soil treatment area. For the business side of these purchases, see our walk-through of pricing septic installation by its cost drivers.

Grade control: laser, builder’s level or transit

Holding grade is the job no one sees until it fails, and it takes an instrument, not an operator’s eye. The University of Minnesota onsite program’s article on excavation and over-excavation advises crews to “Use a laser and verify proper elevations” throughout excavation, which limits the imported backfill needed to support the pipe and tank.

The Missouri guide makes the same point for trenches that follow the contour on sloped ground, where a “builder’s level or transit is critical for such applications.” A laser on a tripod with a receiver on the machine or a grade rod lets the operator dig to elevation without over-digging. That matters because natural soil usually gives the most stable base for system components, and over-excavation replaces that base with fill you have to buy, haul and place.

Tree stumps are a common reason for extra digging. The same University of Minnesota article calls for taking the stump out to a depth 12 to 36 inches under the infiltrative surface, depending on effluent quality and local codes, so your grade instrument has to follow the dig past the stump as well.

Machines that protect the soil treatment area

The drainfield soil is part of the system, and the wrong machine can ruin it before the first pipe is laid. Minnesota’s guidance says “Equipment with low ground pressure should be used” to remove unsuitable materials, and it warns never to backfill an over-excavated infiltrative surface with compactable material.

Moisture matters as much as machine weight. Minnesota’s article on wet-site installs says soil must be dry enough for site-prep and material-handling equipment to operate, and it allows excavation only when soil is below its plastic limit. It defines the risk plainly: “Smearing is spreading and smoothing soil particles by sliding pressure.” Missouri’s guide gives the same rule in field terms, telling installers to build the absorption field “when the soil is crumbly — never wet.”

Plan the traffic pattern so tracked or wheeled machines stay off the treatment area, and keep a low-ground-pressure option for sites where they cannot. If rain falls on an exposed infiltrative surface, Minnesota’s advice is to wait and prepare the surface again, which is a scheduling cost worth building into every bid.

Loaders, skid steers and trenchers

Loaders move the material that the digging machine does not. OSHA’s material handling equipment standard applies its earthmoving rules to loaders, bulldozers, graders and similar equipment, and requires seat belts and service brakes that can hold a full load.

Skid steers occupy an odd place in that standard. The regulation says specific rules for rubber-tired “skid-steer” equipment is reserved, pending standards still being developed, so the general earthmoving requirements and your manufacturer’s manual carry the load. On a septic job, a skid steer or compact track loader typically spreads fill, moves rock and backfills around the tank. A trencher can speed straight distribution lines in the right soil, though it is a supporting machine rather than a substitute for the excavator.

Setting the tank: lifting equipment and the rules around it

Setting a tank is a lift, and the lift is where installation crews face some of the most serious risk. OSHA’s crane standard covers boom trucks and truck-mounted cranes used in construction, and it lists “Power shovels, excavators, wheel loaders, backhoes, loader backhoes, track loaders.” among the excluded machinery, including when they lift with chains or slings.

Even so, OSHA’s excavation rule states that “No employee shall be permitted underneath loads” moved by a digging or lifting machine, which is why tag lines and a clear hole matter on every set. The EPA describes the septic tank as buried and watertight, and on wet sites that creates a second problem: Minnesota’s guidance says tanks set in a known water table need buoyancy calculations, and extremely wet sites may need dewatering before the tank can be set stable. On those sites, a dewatering pump may join the equipment list alongside the digging machine.

Plan the lift before the tank arrives. Confirm with the tank supplier and the machine’s manufacturer that the machine and rigging you intend to use are rated for the load, check the ground where the machine will sit during the set, and keep the crew clear of the hole until the tank is down and the rigging is slack.

Real-World Scenario: An installer set a concrete tank with an excavator and rigging while a laborer steadied it from inside the hole. The tank swung as it was lowered, and the laborer had to scramble out. No one was hurt, but the owner rewrote the crew’s procedure the same week: tag lines only, nobody in the hole during a lift, and a pre-lift check of the rigging and the ground under the machine.

Trench protection and excavation safety

Trench protection is equipment, and on many septic jobs it is required equipment. OSHA’s booklet defines a trench as an excavation deeper than it is wide, with a limited bottom width, which describes most tank holes and many distribution lines. OSHA’s trenching page says cave-ins pose the greatest risk in trenching, and its booklet puts the stakes bluntly: “An unprotected trench can be an early grave.”

The OSHA trenching fact sheet says trenches 5 feet deep or greater require a protective system unless dug entirely in stable rock, and trenches 20 feet deep or greater need a protective system designed by a registered professional engineer. A competent person must inspect trenches daily and after rainstorms. Before digging, the excavation rule requires crews to determine where underground utilities are, and it requires spoil and equipment to be kept at least 2 feet from the edge of excavations under OSHA’s specific excavation requirements, or held back by retaining devices.

OSHA’s booklet adds the simplest rule on the page: “Keep heavy equipment away from trench edges.” Budget for a trench box or shoring system, ladders for egress and a crew member trained to act as the competent person. For installer licensing and permit rules where you work, see our state pages.

Insuring the machines and the work they do

The equipment list above is also an insurance list, because each machine is both an asset you can lose and a source of claims against you. Machines that move from site to site are typically written under contractors equipment coverage, and our explainer on what inland marine insurance does not cover on septic gear walks through the common gaps. A machine you rent for a single job may be treated differently from one you own, and a rental agreement may make you responsible for damage while the machine is in your care, so it helps to ask how rented equipment is handled before the rental arrives on site.

The work itself raises different questions. A struck utility line or a damaged driveway may fall to general liability, while an injured crew member is a workers’ compensation matter, and the trucks hauling your machines belong under commercial auto. How each responds depends on the policy wording. Our page on septic installation insurance shows how installation work is usually written, and a quote request that lists every machine, trailer and attachment gives you the clearest answer.

Questions septic owners ask about this

What equipment do I need to install a septic system?

At minimum, a machine to dig, such as an excavator or a backhoe, plus a laser or builder’s level to hold grade on the tank, pipe and trenches. Add equipment for moving material, such as a loader or skid steer, a safe method for setting the tank, and trench protection for deep excavations. Soft or sensitive sites may call for low-ground-pressure machines. The exact list depends on the system type your design calls for.

Do I need an excavator or a backhoe to set a septic tank?

Either can dig the hole, and extension guidance describes backhoes digging both soil pits and absorption trenches. The choice usually comes down to site access, reach, the soil and what you already own. For lifting, remember that OSHA’s crane standard excludes excavators and backhoes even when they lift with chains or slings, but its excavation rule still bars anyone from standing under a load. Plan the lift before the tank arrives.

Can I install a septic system with a skid steer?

A skid steer is useful for moving spoil, spreading fill and backfilling, but it is rarely the only machine on the job. OSHA’s earthmoving rules cover loaders, bulldozers and graders, while specific skid-steer rules are reserved pending future standards. Weigh the machine against the soil treatment area, too, because guidance from Minnesota’s onsite program favors low-ground-pressure equipment to limit compaction there.

What license do I need to install septic systems?

Installer licensing depends on your state and often your county, and the requirements vary widely from one territory to the next. A state credential, a county certification and a permit for each individual system can all apply to the same job. Check the rules for your territory on the state pages before you buy equipment or bid work, since a license may limit which system types you are allowed to install.

Do I need trench boxes or shoring on a septic job?

It depends on depth and soil. OSHA requires a protective system for trenches past its depth threshold unless the excavation is entirely in stable rock, and deep excavations need a system designed by a registered professional engineer. A competent person must inspect trenches daily and after rainstorms. Tank holes and distribution boxes often reach depths where protection applies, so plan for shoring, sloping or a trench box before digging.

How do I insure my excavator and other septic equipment?

Machines that move from job to job are usually written under contractors equipment coverage, often called inland marine, rather than a building policy. How a policy responds depends on its terms, including how it treats theft, overturn and mechanical breakdown. Listing every machine, trailer and attachment with its value when you request coverage, and revisiting that schedule whenever you buy, sell or rent a machine, can help keep the equipment schedule accurate.

About the author